Fort Riley

Fort Riley

Location: Fort Riley

Client: United States Army Corps of Engineers – Kansas City District

Completion: 2023

Value: Project Value: $1,245,061.00

Highlights

  • Nature of firm’s responsibility: Compass Constructors worked as the Prime Contractor for this project.
  • Project Schedule: Compass Constructors achieved substantial completion in late Summer of 2023.  This project was delivered 45 days ahead of schedule.
  • Type of Contract: 8(a) Sole Source Negotiated Agreement – Firm Fixed Price

This project consisted of the storm damage roof replacement of Facilities 7808 and 7485. Specifically, it consisted of the replacement of a total of 885 sqs of modified bitumen roof system and removal/replacement of the existing roof related sheet metal flashing and trim.  The specific features of work contained within the project were selective demolition, structural deck repair, SBS modified bitumen roof installation, and roof related sheet metal removal and replacement.